December 14, 2021
Construction Update 3 - Construction and renovation activity continued this week here at the Millville VFC. Construction of interior walls continued and preparations for the structural steel that will support the roof trusses continue in the new section. In the existing section of the building, removal of the old ceiling grid, insulation, and duct work are almost complete. The existing kitchen floor and old hood system were removed. The meeting/training room has been expanded to allow for more seating capacity. Hoping for roof trusses and sprinkler installation in the near future.